A customer account · Massachusetts · 2026

Four months after HomeWorks Energy damaged my home, I'm still waiting for them to pay for the repairs.

I hired HomeWorks Energy through Mass Save to install a heat pump system. The install left water damage in two floors of my house, took nearly three months and four visits to finish, and as of today the company has not paid a dollar of the repair costs it agreed in writing to cover.

Everything below comes from my own email correspondence with HomeWorks and its subcontractors. Dates are from those emails; quoted text is verbatim. Last updated October 16, 2026.

102 dayssince I first sent HomeWorks photos of the water damage
4 visitsto get the system's controls working, ~12 weeks after install
7 roomswith damage from the install, leak, or HomeWorks' repair crew
$0paid of the $3,025 HomeWorks agreed to cover on Oct 6

The short version

The heat pump install was scheduled, rescheduled, and started late. A part was missing, so the new system couldn't talk to my thermostats. When a technician came back to finish the job and turned the system on, water from the installation leaked into my ceilings, staining a first-floor living room and a second-floor bedroom closet. The closet developed a persistent musty smell.

HomeWorks sent a remediation company and a drywall/paint subcontractor. The subcontractor's ceiling patch didn't match, water stains were still visible, paint went onto the moulding, and the floor got scratched. Meanwhile, the second technician sent to finish the controls told me he'd never seen the equipment before and didn't know how to install it.

I eventually got two independent repair quotes myself. HomeWorks agreed to cover $3,025 of them, then spent the next ten days telling me it was "still waiting on the agreement letter." After I escalated to senior leadership, I was told the team would follow up that day. Nobody did.

Timeline

  1. Signing and scheduling
  2. Apr 6–8

    Signed the proposal and paid a $500 deposit. The project was financed through a Mass Save HEAT Loan.

  3. Apr 13

    Told HomeWorks that the coordinator assigned to my project, who called me, didn't seem familiar with basic details of the job. HomeWorks apologized for "any confusion."

  4. May 18

    Per HomeWorks' loan process, I endorsed the loan check over to HomeWorks and mailed it. The project was effectively paid before any work started.

  5. May 21

    HomeWorks confirmed a four-day install, June 9–12.

  6. Jun 5

    HomeWorks' confirmation now listed only June 10–12. I pointed out it had been booked as four days.

  7. The install
  8. Jun 9

    The crew didn't start as scheduled. HomeWorks emailed that afternoon saying they'd come the next three days instead.

  9. Jun 10–12

    System installed, but a part needed to connect it to my existing thermostats and boiler was missing. The thermostats could only see the old boiler.

  10. Jun 15–22

    I followed up repeatedly about the missing part. HomeWorks installed a basic stopgap thermostat on June 25 and booked the controls integration for July 1.

  11. Jul 1

    Integration attempt #2. The technician turned the system on.

  12. The leak
  13. Jul 6

    After discovering water stains, I sent HomeWorks photos of damage to the first-floor ceiling, the second-floor closet ceiling, and the attic.

  14. Jul 8

    Asked, in writing, for an independent water-restoration evaluation at HomeWorks' expense, given a persistent smell in a bedroom closet and possible mold. Reported a new stain later that day.

  15. Jul 9

    After 24 hours with no written reply, I set a deadline. HomeWorks replied:

    "I also want to reassure you that you have not been ignored."
    I asked HomeWorks to stop responding to my emails by phone and put things in writing.

  16. Jul 10

    A remediation company inspected. Remediation work didn't start until mid-August.

  17. Jul 15

    Integration attempt #3. The technician told me he had never seen this integration equipment and didn't know how to install it; he expected to be trained on it the following week.

  18. Jul 22 – Aug 5

    Two weeks of follow-ups ("I know you're reading this") before HomeWorks proposed a date.

  19. The repairs
  20. Aug 12–13

    Remediation opened the closet wall; HomeWorks' drywall/paint subcontractor followed.

  21. Aug 25

    The repair was inadequate. The patched textured ceiling didn't match the original, water stains were still visible, paint was applied onto the moulding, and the living-room floor was scratched. The closet was rebuilt with nail holes and gaps left unfinished.

  22. Aug 27

    HomeWorks cancelled the integration visit the morning of, citing an emergency call. Nobody came.

  23. Sep 3

    Integration attempt #4 finally completed, and the drain line was relocated away from the storage space. About 12 weeks after the install.

  24. Sep 7

    Sent HomeWorks a written, photo-documented list of remaining damage across seven rooms. Also noted that two air purifiers (about $2,000) included in the contract were never installed.

  25. Sep 14–18

    Reported that with the thermostat set to 65°F, the house wouldn't drop much below 75°F, with thermostat data to show it. The project manager first suggested the thermostat schedule was to blame, then asked me to call.

  26. The reimbursement
  27. Sep 29

    Sent HomeWorks two independent repair quotes I'd gathered myself: $3,405 and $3,475.

  28. Oct 6

    HomeWorks agreed to cover $3,025, excluding items it called

    "unrelated to the leak and resulting damage."
    The excluded items were holes and damage in ceilings next to the vents and ductwork HomeWorks installed.

  29. Oct 7

    HomeWorks said it would seek approval "today."

  30. Oct 8–15

    Five written reminders from me. Replies included:

    "Unfortunately I am still waiting on the agreement letter for us to sign."
    "My apologies for the delay, I will find out what is holding up this process!"

  31. Oct 15

    Escalated to HomeWorks senior leadership.

  32. Oct 16

    Leadership replied:

    "That is not the level of service we aim to provide. … They assured me that they will be following up today."
    No one followed up that day.

What HomeWorks agreed to cover vs. what it excluded

Repair (from an independent quote)QuoteHomeWorks
Living room ceiling: sand, skim coat, prime and paint$2,225Covered
Living room wall: crown moulding, water stain, repaint$410Covered
Primary bedroom: drill damage in ceiling, wall, moulding$190Covered
Bedroom closet: baseboards, shelf, bracket$200Covered
Primary bathroom: ceiling around exhaust fan$75Excluded
Upstairs hallway: two ceiling holes from the HVAC work$100Excluded
Guest bedroom: ceiling around new vent$125Excluded
Second bedroom: ceiling around new vent$80Excluded
Agreed Oct 6 · paid as of Oct 16$3,025$0

The excluded items weren't caused by the leak, but they were caused by the install. Every one of them is next to ductwork or equipment HomeWorks put in. HomeWorks' field team told me during an end-of-install walkthrough that they'd be fixed.

Still unresolved

If you're considering HomeWorks Energy

  1. Get everything in writing. Staff repeatedly replied to my emails by phone. When things go wrong, a phone call is your word against theirs.
  2. Know when your money leaves. Under the HEAT Loan process, my loan check went to HomeWorks before any work started. After that, I had no payment leverage.
  3. Photograph every room before the install, especially ceilings near where ducts, vents, and air handlers will go.
  4. Ask who will actually do the work. My install, repairs, and project management involved several outside subcontractors.
  5. Don't sign off on completion until every part of the system is installed and working, including the controls and anything else in your contract.
  6. Escalate early. Mass Save (the program HomeWorks works under) and the Massachusetts Attorney General's consumer complaint process both exist for this.